Pack_Mule wrote:Any idea how long it will take to find out what/IF we got a permit??
It could be well into April. Hard to say since this is another "new system" they are implementing.
Some of it depends on where you fell in the draw and the itinerary you chose.
my 2 cents
pete
Belly River trip
Date Window--June 15-July 15
Enter CME
Night 1 COS (GAB will work just as well)
Night 2 MOJ (Where I sleep doesn't matter. Just need a "base camp" and prefer to not move around every day)
Night 3 MOJ (for day hikes to Margaret Lake and Sue Lake overlook areas for photos)
Night 4 MOJ
Night 5 GAB
Choice 2 is
Enter Cut Bank
Night 1, 2,3 at Atlantic Creek Day hikes up to Divide Pass and Divide Mt and maybe Medicine Grizzly Lake for photos
Out Cut Bank
On a separate application I put in for this with a window of Aug 10 to Sept 10:
In at BOU
Night 1 UPK
Night 2 BOU
Night 3 BOU
Night 4 KIN
Out BOU
teapot57 wrote:This will be the least stressful March 15th morning that many of us have had since 2015. But as tibber pointed out to me, the anticipation after submitting will be far greater, not knowing where your permit will land in the draw.
In the old manual system you didn't know where you landed in the draw for some weeks. You waited on your email. So similar?
And yeah, it was pretty painless since you weren't watching the stupid clock waiting to click on the hour!